試題題型【單選題】
試題內容

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (  ) progress.
A. analyze
B. track
C. level
D. extend