To meet the schedule,a decision was made to outsource part of a project to an external manufacture. What steps should a project manager follow to assess potential suppliers before awarding a contract?
A、Bidder conferences,independent estimate,and procurement negotiations
B、Quantitative analysis,bidder conferences,and critical path analysis
C、Procurement negotiations,independent estimate,and performance report
D、Procurement performance review,expert judgment and proposal evaluation technique