久久久久久做,国产69精品久久久久999天美,一级毛片生活片,国产在线欧美在线,日本黄色一级片免费看,欧美黄色1级视频,少妇高潮av久久久久久

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-3
考試中心《信息系統(tǒng)項目管理師-pmp練習題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

In an eight-month project, the customer requests a change to a complex business requirement. Development is 72% complete. The customer suggests the project schedule be extended by an additional month. What should the project manager do next?
A、Reject the change since most of the development is complete.
B、Ask for additional funds.
C、Analyze the variance.
D、Accept the change since the customer has increased the schedule.


相關試題

推薦文章
合作網站內容