A project manager noticed that the work groups are not collaborating. Because they don’t know the most recent information causing delays in some activities. What should the project manager do next ?
A、Distribute weekly status reports to the work groups.
B、Revises the communications management plan.
C、Schedule a project meeting to share the latest information.
D、Escalate the issue to the project sponsor.